News, News-buzz

Update on roofing project at St. Jude Hospital

Image of St. Jude hospital(PHOTO BY: PhotoMike)

THE Board of Directors and Management of the St. Jude Hospital have sought to reassure staff and clients of their commitment to ensure quality health and safety standards are maintained during the removal of the current fiberglass roof at the George Odlum Stadium.

One glance at the loose sheeting on the roof of the George Odlum Stadium emphasises the potential hazard to staff and clients at the St. Jude Hospital.

Government has contracted the services of Brice and Company to remove the fiberglass sheeting, guided by the British standard for demolition agreed to for the project.

CEO of Brice and Company, Eaton Jn Baptiste, said the company has met all the requirements of government and St. Jude with reference to the works, including the method statement and insurance certificate.

He said his company has the competence and track record to deal with the project, having been in the roofing business for the past 18 years.

According to Jn Baptiste, ā€œWeā€™ve been around that type of roofing system.

ā€œFiberglass is a material that is used with various other materials. There is a percentage in the roof; it is basically a plastic roof.

ā€œThere is a percentage of fiberglass you would find in a regular shingle roof on a house that we remove every day. So, we are equipped to deal with it.

ā€œWe have dealt with it before in the past and our workers would always adhere to all the safety requirements where that is concerned in terms of the safety gear, the necessary safety harnesses and so on. We adhere to the procedures where that is concerned fully.ā€

Based on the work done thus far, the contractor is confident of completing the project in less than half the estimated time.

ā€œWe started this about a week ago and we have not had a complete five days of work on it.

ā€œThere have been some disruptions here and there, but 80% of the work is done.

ā€œInitially, the ministry and the government expected us to be there for about three months, but we rather suspect weā€™re going to cut it [the time] in half — or a little less.ā€

Verna Charles, CEO at St. Jude Hospital, said there is on-going monitoring and evaluation of the project by management of the hospital and the contractor.

ā€œWithin one week, everything was going on fine. But halfway during the course of the second week we experienced some challenges with our staff on compound and as was reported in the first press release that anything with the project that would compromise the health of our staff, our patients, visitors we would go back to the drawing board and revisit the scope of work and to implement new interventions to ensure the safety of all concerned.

ā€œSo, this is what we have done thus far.ā€

Chairman of the Board of Directors at the St. Jude Hospital, Wayne Harrow, said the board remains concerned and directly involved the with works happening on the ground.
He said, ā€œā€œWe wish to state also that the health and safety of all concerned is and remains our first priority.

ā€œThe patients, the visitors — and of course our professionals who deliver quality health services to our patientsā€¦ We wish to say that their safety remains our first priority.

ā€œWe will continue to collaborate with all stakeholders to ensure that whatever decisions we take benefit every single person, whether youā€™re staff, whether youā€™re staff, a patient or a visitor. This remains our first priority.ā€ (Ministry of Health)

1 Comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Send this to a friend